9. Stoppage or Demolition:
9.1 In cases where a person, carries out, without the prior approval of the
Authority, any activity being regulated, controlled or prohibited by the
Authority under section 8 or carries out any activity in violation of the
terms and conditions specified by the Authority while giving
approval, the Authority may order to stop the activity forthwith and if
any thing was constructed in the course of carrying out such activities,
the Authority may, by giving a notice of thirty five days, order the
person concerned to demolish or remove the part so constructed
without approval or in violatoin of the terms and conditions.
9.2 A person not satisfied with the order issued by the Authority pursuant
to sub-section 9.1 to demolish or remove any part of any structure
may file a complaint to the appellate committee within thirty five days
from the date of receipt of such order. The appellate committee shall
make decision on the complaint within thirty days of the filing of the
complaint and such decision shall be final.
9.3 In cases where a complaint has been filed pursuant to sub-section 9.2
and decision has been made by the Appellate Authority to demolish or
remove the part of the structure, the person concerned shall demolish
or remove the part of the structure within thirty five days of such
decision and if no complaint has been filed, within thirty five days
from the date of the issue of the order issued by the Authority
pursuant to sub-section 9.1.
9.4 If a person concerned does not demolish or remove the part of the
structure with the time period stipulated in sub-section 9.3, the
Authority may demolish or remove it on its own and any cost
involved in such demolition or removal shall be recovered from the
person concerned.